Project progress

Confirmed milestones and updates.

Key information on the delivery of the Rietavas battery energy storage facility.

2025 Q2Capacity reservation
01

Letter of intent signed with Litgrid

The letter of intent reserved the grid capacity required for the project.

2025 Q2Development permit
02

VERT issued the energy storage development permit

The National Energy Regulatory Council issued the permit required to develop the project.

2025 Q3APVA funding
03

Funding agreement signed with APVA

The project was awarded financing from the European Union Modernisation Fund under a measure administered by APVA.

2025 Q4Building permit
04

Building permit obtained

The construction permit required to deliver the project was issued.

2025 Q4EPC contract
05

€27.8 million EPC contract signed

MT Group will engineer, construct and commission the Rietavas battery energy storage system.

2025 Q4Financing
06

Artea Bank finances the project

The financing partnership provides a strong foundation for the delivery of strategically important energy infrastructure.

2026 Q1Earthworks
07

TETAS commenced active earthworks on site

Site preparation and the principal earthworks commenced.

2026 Q3Equipment delivery
08

All critical equipment delivered to site

Power conversion systems (PCS), batteries and other essential BESS equipment arrived on site.

2026 Q3Cold commissioning
09

Cold commissioning begins

System checks and cold commissioning are scheduled to begin before power is supplied to the grid.

2026 Q4Planned
10

Energisation

The project’s electrical equipment is scheduled to be energised, enabling the next commissioning stage.

2027 Q1Planned
11

Generation permit

The generation permit is planned to be obtained.